TIP ID | Project Name | Project Description |
Sponsoring Agency
| Managing Agency | Project Location | Design Phase | Design Cost | ROW Phase | ROW Cost | Construction Phase | Construction Cost |
U-5501A | Reedy Creek Road Improvements | Project consists of Right-of-Way acquisition along Reedy Creek Road from NE Maynard Road to North Harrison Avenue (Segments A&B) and Construction along Reedy Creek Road from North Harrison Avenue to 600 feet south of Watts Pond Lane (Segment A) for improvements to the facility. Improvements will include widening the current facility from 2 to 3 lanes, the addition of a center turn lane, curb and gutter, sidewalks, bike lanes and three roundabouts. |
Cary
| Same as Sponsoring Agency | Cary | | $0.00 | | $1,280,000.00 | | $5,117,500.00 |
| Holly Springs Road Widening | Project consists of Design, Preliminary Engineering, and Right-of-Way acquisition along Holly Springs Road from Jones Franklin Road to SE Cary Parkway for widening of the facility. Improvements will include widening the current facility from 2 to 4 lanes, the addition of a landscaped median including curb and gutter and sidewalks. |
Cary
| Same as Sponsoring Agency | Cary | | $500,000.00 | | $350,000.00 | | $2,800,000.00 |
| Harris Road Operational Improvements | Construction for a single-lane roundabout and pedestrian facilities at the intersection of Harris Road (SR 1931) and W. Oak Ave (SR 1931)/Wall Rd (SR 1932). The proposed improvements include installing a roundabout with associated curb & gutter, stormwater, realigning a portion of Harris and Wall Roads, adding approximately 2,700LF of sidewalk on Wall Road to Wallridge Drive (Wallridge Subdivision) and 350LF sidewalk from Wall Road to existing sidewalk at Harris Point Way (Harris Point subdivision). Minimal right of way is needed; less than 10 parcels are impacted by this improvement project. |
Wake Forest
| Same as Sponsoring Agency | Wake Forest | | $0.00 | | $0.00 | | $2,548,558.00 |
U-5317 | Connect N Judd Parkway NW | Project consist of construction phase of approximately 2.2 total miles with 1.8 miles of new roadway location with four lanes with median and left turn lane at intersections for both the new location roadway and the existing roadway improvement for a portion of Wilbon Road (SR 1110) to be known as N Judd Parkway NW from NC 55 (North Broad Street) to NC 42 (West Academy Street) that will include accommodations for bike and pedestrian access and travel. Also included is intersection relocation for Wilbon Road (SR 1110) with new roadway and extension of Washington Street (Town Street) to the new roadway that provide improved access to Lincoln Height Neighborhood, an economically depressed area of the Town with greater and more convenient access to Town’s services and to the overall community. FONSI issued May 31, 2016 and Roadway Design for this project will be completed by end of 2016. Right-of-Way Phase LAPP funding was granted in FY 2017, NCDOT local administration agreement is completed and right of way obligation request has been submitted and pending. |
Fuquay-Varina
| Same as Sponsoring Agency | Fuquay-Varina | | $1,500,000.00 | | $5,900,000.00 | | $18,800,000.00 |
| Morrisville-Carpenter Road Widening | Widening of Morrisville-Carpenter Road between the railroad crossing west of NC 54 and Davis Drive. New widening is needed from 300 feet west of Old Savannah Drive to the railroad tracks. The remaining work from Old Savannah Drive to Davis Drive will consist of repaving and re-striping the existing roadway to a four-lane, median-divided road with center left-turn lanes where
appropriate. As part of this project, the Town will also be relocating utilities in the widening portion of the project, between Old Savannah Drive and Page Street, which is why the Right-of-Way phase is included (all other parts of the Right-of-Way phase will be completed with Town funds). According to estimates received from Duke Energy-Progress, Utility Relocation will cost $1,500,000 for burying utilities. If possible, the Town will relocate the utilities underground; however due to cost and timing, the Town may have to relocate the utilities above-ground. The Town has funded Engineering/Design, Permitting and Right-of-Way Acquisition for the project. |
Morrisville
| Same as Sponsoring Agency | Morrisville | | $901,500.00 | | $1,965,000.00 | | $7,035,000.00 |
| Sunset Lake Road Improvements | The project consist of Design and Right of Way acquisition along Sunset Lake Rd (SR 1301) from west of Lockley Road to Kenmont Drive. Improvements will include widening approx 0.91 miles of the existing facility including additional lanes, landscape median, sidewalk, bicycle lanes, curb and gutter |
Holly Springs
| Same as Sponsoring Agency | Holly Springs | | $500,000.00 | | $1,000,000.00 | | $7,000,000.00 |
| Wade Ave at Ridge Rd | Dual left turn lane on Wade Avenue at Ridge Road |
Division 5
| Same as Sponsoring Agency | Raleigh | | $90,000.00 | | $10,000.00 | | $400,000.00 |
| Airport Blvd Extension | Extend Airport Blvd from Garden Square Lane to Church Street. |
Division 5
| Same as Sponsoring Agency | Morrisville | | $500,000.00 | | $400,000.00 | | $3,000,000.00 |
| Ten Ten Road at Holly Springs Road | Improve intersection of Ten Ten Road and Holly Springs Road by adding an EB auxiliary through lane, dual SB left turn lane, and a northbound auxiliary through lane. Intersection is in Wake County and some of the project is in Cary. |
Division 5
| Same as Sponsoring Agency | Wake County | | $450,000.00 | | $450,000.00 | | $1,600,000.00 |
U-2719 | I-440 Betterments | NCDOT project to widen I-440 in SW Raleigh from two lanes to three. The project brings several aspects of the highway that are substandard up to current best practices while increasing capacity in a highly congested corridor. City participation in the project will improve the project. Areas for improvement include, but are not limited to: median treatments, interchange modifications, modifications to grade separations, noise wall treatments, and non-motorized connections. |
Raleigh
| Division 5 | Raleigh | | $0.00 | | $1,000,000.00 | | $4,000,000.00 |