2019 Roadway Projects

TIP IDProject NameProject Description Sponsoring Agency Managing AgencyProject LocationDesign PhaseDesign CostROW PhaseROW CostConstruction PhaseConstruction Cost
 Poole RoadThis project would extend the previous improvements along Poole Road east of Maybrook Road to Barwell Road. The project is currently in design and would include widening the street to a four-lane median-divided section and the installation of curb & gutter, sidewalks, bicycle facilities, streetlights, and landscaping. Raleigh Same as Sponsoring AgencyRaleigh$881,000.00$3,300,000.00$6,500,000.00
 Harris Road Operational ImprovementsConstruction for a single-lane roundabout and pedestrian facilities at the intersection of Harris Road (SR) and W. Oak Ave. (SR 1931)/Wall Rd (SR 1932). The proposed improvements include installing a roundabout with associated curb & gutter, stormwater, realigning a portion of Harris and Walls Roads, adding approximately 2,700 lf of sidewalk on Wall Road to Wallridge Drive (Wallridge Subdivision) and 350 lf of sidewalk from Wall Road to existing sidewalk at Harris Point Way (Harris Point Subdivision). Required Right-of-Way is minimal; less than 10 parcels are impacted by this improvement project. Wake Forest Same as Sponsoring AgencyWake Forest$0.00$0.00$1,987,756.00
 Old Honeycutt/Purfoy Road Intersection ImprovementsThis Project consists of improving the intersection by potentially adding turning lanes, modifying signal timing, adding phases to the signals, and adding pedestrian crossings and signals. Fuquay-Varina Same as Sponsoring AgencyFuquay-Varina$136,500.00$120,000.00$962,000.00
U-5501Reedy Creek Road Improvements Phase 2This construction project is the 2nd phase of the Reedy Creek Road widening project extending from N Harrison Ave to NE Maynard Rd. Phase 1 is funded in FY18 and consists of ROW acquisition throughout the corridor and construction of Segment A, N Harrison Ave to 600 ft south of Watts Pond Lane. Phase 2 will construct Segment B from 600 ft south of Watts Pond Lane to NE Maynard Rd. The construction project widens Reedy Creek Road from a 2-lanes to a 3-lane cross-section with curb and gutter, center turn lane, 2 roundabouts, bike lanes, and sidewalks along both sides of the corridor. Cary Same as Sponsoring AgencyCary$0.00$0.00$6,720,000.00
 Old Wake Forest Road NorthThis project will widen Old Wake Forest Road to a four-lane median-divided section from Atlantic Avenue to Capital Boulevard. The project scope will include curb & gutter, sidewalks, bicycle facilities, and streetlights. Raleigh Same as Sponsoring AgencyRaleigh$1,099,000.00$3,707,000.00$8,600,000.00
 Tryon Road Part CThis project would widen Tryon Road to a four-lane median-divided section from Lake Wheeler Road to the bridge over the Norfolk-Southern Railroad, which was recently replaced and widened. The project scope will include curb & gutter, sidewalks, bicycle facilities, streetlights, and landscaping. This project is currently in design and is the last portion of Tryon Road remaining to be widened. Raleigh Division 5Raleigh$1,048,000.00$3,425,000.00$6,800,000.00
 New Bern Avenue Bottleneck EliminationConstruct approximately 500 feet of a third lane on New Bern Avenue to provide a consistent three lanes eastbound. Project will include curb and gutter and sidewalk from start to end point. Raleigh Same as Sponsoring AgencyRaleigh$70,000.00$50,000.00$400,000.00
 Holly Springs Rd. WideningThis project will widen approximately 350 LF of westbound Holly Springs Road to match flanking sections of roadway. The project will provide a missing link of sidewalk as well. Holly Springs Same as Sponsoring AgencyHolly Springs$0.00$0.00$335,000.00
 Connected Vehicle TechnologyThe Town plans to expand a joint NCDOT-Cary Signal Phasing and Timing (SPaT) project by adding Connected Vehicle (CV) technology town-wide with additional Vehicle to Infrastructure (V2I) safety measures. This ITS project would upgrade existing traffic signal controllers, install Road Side Radio Units (RSUs), and implement a CV software suite to allow Town staff to communicate with drivers about roadway and operational conditions; allow vehicles to share data with Town staff such as speed, volume, and delay; and improve efficiencies through the retrieval of high definition data. Funding would provide for new equipment and software to operate approximately 100 traffic signals in the Town’s ATMS. The RSUs will be placed along major thoroughfares, including US and NC routes, as well as strategic corridors within the Town. The $400,000 of matching funds associated with this grant request is programmed within FY 2019 of the Town’s capital improvement plan. Cary Same as Sponsoring AgencyCary$0.00$0.00$2,000,000.00
 Main St. & Holly Springs Rd. Safety Improvements ProjectThis project will install Rectangular Rapid Flashing Beacons, (RRFB) warning signs at 8 locations throughout Holly Springs. Holly Springs Same as Sponsoring AgencyHolly Springs$0.00$0.00$375,300.00